Rhode Island

Rhode Island notice of intention

In Rhode Island, every claimant, at any tier, must mail a Notice of Intention by registered or certified mail and record it in the land evidence records. It covers only work done within the 200 days before it is mailed and recorded, so on a long job give it early and repeat it as needed (R.I. Gen. Laws § 34-28-4). Separately, a contractor who deals directly with the owner (other than a material supplier) must give the owner a Notice of Possible Mechanic’s Lien before starting work, or it cannot claim a lien (§ 34-28-4.1).

Flat fee of $49. Your instructions say who receives it, how, and by when.